The Estimate Activity Resources process has the following Inputs, Tools and Techniques and Outputs 


InputsTools and TechniquesOutputs
Activity ListExpert judgmentActivity resource requirements
Activity attributesAlternative analysisResource breakdown structure
Resource calendarsPublished estimating dataProject document updates
Enterprise environmental factorsBottom-up estimating
Organizational process assetsProject Management software


المحتوى العلمي مقدم من


Courses Coffee Training Center

14 مصطفى النحاس – عمارة البنك الأهلي المتحد –
 بجوار شاورمة أبو مازن – مدينة نصر

010-10531215
011-00616646
011-23366277

Sequence Activities Process - PMP - ادارة المشاريع


Sequence Activities Process
The Sequence Activities process has the following Inputs, Tools  and Techniques and Outputs 

InputsTools and TechniquesOutputs
Project scope statementPrecedence diagram method (PDM) or AONProject schedule network diagrams
Activity ListApplying leads and lagsProject document updates
Activity attributesSchedule Network Templates
Milestone listDependency determination
Organizational process assets


المحتوى العلمي مقدم من


Courses Coffee Training Center

14 مصطفى النحاس – عمارة البنك الأهلي المتحد –
 بجوار شاورمة أبو مازن – مدينة نصر

010-10531215
011-00616646
011-23366277

Define Activities Process - PMP - ادارة المشاريع


Define Activities Process
The Define Activities process has the following Inputs, Tools and Techniques and Outputs 


InputsTools and TechniquesOutputs
Scope baselineDecompositionActivity list
Enterprise environmental factorsRolling wave planningActivity attributes
Organizational process assetsTemplatesMilestone list
Expert judgment




المحتوى العلمي مقدم من


Courses Coffee Training Center

14 مصطفى النحاس – عمارة البنك الأهلي المتحد –
 بجوار شاورمة أبو مازن – مدينة نصر

010-10531215
011-00616646
011-23366277

Time Management Processes - PMP - ادارة المشاريع



Time Management Processes

The knowledge area of Project Time Management consists of the following processes -

ProcessProject PhaseKey Deliverables
Plan Schedule ManagementPlanning
Define ActivitiesPlanningActivity List, Milestone list
Sequence ActivitiesPlanningProject Schedule network diagrams
Estimate Activity ResourcesPlanningActivity resource requirements,
Resource breakdown structure
Estimate Activity DurationsPlanningActivity duration estimates
Develop SchedulePlanningProject Schedule
Control ScheduleMonitoring and ControllingWork Performance measurements,
Change Requests


المحتوى العلمي مقدم من


Courses Coffee Training Center

14 مصطفى النحاس – عمارة البنك الأهلي المتحد –
 بجوار شاورمة أبو مازن – مدينة نصر

010-10531215
011-00616646
011-23366277

Project Time - PMP - ادارة المشاريع



Project Time / Schedule Management


1-Time Management Processes.

2-Define Activities Process.  

3-Sequence Activities Process.

4-Estimate Activity Resources Process.

5-Estimate Activity Durations Process.

6-Develop Schedule Process.

7-Control Schedule Process.

  1. المحتوى العلمي مقدم من


    Courses Coffee Training Center

    14 مصطفى النحاس – عمارة البنك الأهلي المتحد –
     بجوار شاورمة أبو مازن – مدينة نصر

    010-10531215
    011-00616646
    011-23366277